Work completed in the last two weeks:

  • Townline Avenue and two lanes of Red Arrow Highway temporarily paved and traffic restored.
  • Red Arrow Highway reduced to one-lane traffic in both directions.
  • Outer northbound lane of Red Arrow Highway removed.
  • Dewatering equipment installed along length of Red Arrow Highway.
  • Excavation for MH #4 commenced.

 

Summary of activities expected for next week (July 13 – 18):

  • Install MH #4
  • Install remaining sanitary sewer in Union Pier intersection