The focus this week continued to be on Phase II sanitary sewer mainline and laterals. Next week, work will continue on Phase II sanitary sewer mainline and laterals, as well as Phase II storm sewer and asphalt milling on Phase III.

 

Work Completed This Week

  • Contractor continued placing sanitary sewer mainline on Phase II.
  • Contractor continued placing sanitary laterals to homes on Phase II.
  • Contractor placed new water service to High School boiler bldg.

 

Anticipated Work Next Week

  • Continue placing sanitary mainline on Phase II.
  • Continue placing sanitary laterals to homes on Phase II.
  • Begin placing storm sewer on Phase II.
  • Milling of asphalt on phase III (Southern Ave. to Laketon Ave). Milling is currently scheduled for Monday morning (7/17).
  • Curb & gutter, driveways, and sidewalk removals on Phase III.