This Week:
- K&R finished water main installation along Leelanau and worked on installing water main across Leelanau at the park driveway.
- K&R continued installing new 15-inch sanitary sewer in Northville.
- Northville was closed to thru traffic between Lakehurst and Leelanau, and Leelanau was closed to thru traffic.
- K&R has completed the water main installation across Leelanau at Keeweenaw.
Next Week:
- K&R will pressure test and disinfect the new water main in Leelanau.
- K&R will continue 15-inch sanitary sewer installation in Northville.
- K&R will begin sanitary sewer lateral replacement in Northville starting at Lakehurst.
- Thursday (7/21) – Northville from Leelanau to 5 Mile will be pulverized.
- K&R will remove mailboxes on Northville between Leelanau and 5 Mile. There will be a temporary bank of mailboxes set up on Manitou between Northville and Leelanau where your mail will be delivered once the mailboxes are removed.
- Northville will continue to be closed to thru traffic between Lakehurst and Leelanau, and Leelanau will continue to be closed to thru traffic.
Please contact any project representative if you have questions or concerns.