Work completed/in progress from the last update:

  • Transmission main installation between 144th and River has progressed to Devon Self Storage and will be in front Holland Charter Township maintenance building next week.
  • Transmission main installation between 152nd and 144th has progressed nearly to the recently installed Pine Creek crossing pipe.
  • Area between 160th and 152nd seeded and mulched.
  • Road building behind transmission main construction between 152nd and 144th continued.
  • Installed some 16″ Holland Township water main between Aniline and River.

 

Anticipated activities for the upcoming week include:

  • Continue transmission main between 144th and River.
  • Continue transmission main between 152nd and 144th.
  • **July 20th – Shut down 144th Ave intersection and begin transmission main installation from east side of intersection to Pine Creek. Intersection will be closed for approximately two weeks.**
  • Pressure test transmission main from 152nd to creek crossing.
  • Start easement storm sewer construction for road reconstruct project between 144th (Division) and Aniline.
  • Continue 16″ Holland Township water main installation between Aniline and River.
  • Continue road building between 152nd and 144th.
  • Dewatering setups, lateral replacement, and water service replacement, as necessary.