Progress Update

The standard procedures for water main testing and disinfection are complete with water samples from the new water main passing the required bacteriological tests.  One final water main connection at Colfax and Eloise Drive remains to be completed this coming Monday.  Five of the seven water service lines have been installed. Road restoration work is underway. The concrete curb and gutter was poured today. The concrete base course pavement in the street is scheduled to be poured tomorrow.  The project is on schedule for substantial completion by the end of next week.