Work Completed This Week
- Completed placing sanitary sewer mainline in the easement and in Glen Ave.
- Connected to the existing 10” clay sewer, towards the east end of project.
- Began placing sanitary sewer mainline south on Westwood St.
Anticipated Work Next Week
- Continue placing sanitary sewer main line in Westwood St.
- Begin to connect some sanitary laterals to homes on the west side of Westwood St.
- Begin to place water main, starting at East end of project, on Glen Ave.
Current Road Closures
- Westwood St. is closed to through traffic from Wickham Dr. to Randolph Ave.
- Lexington Ave. is closed to through traffic at Westwood St.
- Randolph Ave. is closed to through traffic at Westwood St.
The contractor anticipates working tomorrow, Saturday July 18.