This week, sanitary sewer removal and replacement is scheduled to start on Pipestone Road.
The project is broken up into a total of four phases, with Phase 1 being the installation of sanitary sewer on Pipestone Road from Herr Court to Carlton Ave, and on Carlton Ave from Pipestone Road to M139. Traffic on Pipestone Road will be maintained with a single lane open in each direction. Carlton Ave will be closed. Traffic on M139 will remain open.