This week, the contractor completed the removal of the sidewalk and curb on the south side of the road. Pipe materials were delivered to the site and the water main began to be installed. The new 16-inch water main was installed from Getty up to Madison Street.

Here is what to expect next week, the week of July 22, 2019

No work is planned for Saturday, July 20, 2019, but Saturday work may be an option to maintain the schedule in the future.
Hydrant branches will be installed off the new water main between Getty and Madison Streets
The new water main will be filled and tested while the other half of the water main will be installed between Madison and Bailey
Water main tie-ins may happen the week of July 29 which will involve some temporary water disruptions. Further information and notice will be given next week as we know more on the progression of the schedule.
More materials will be delivered to the site
Remember that all work is weather dependent.

One paved lane remains for accessing homes and businesses on Broadway within the construction zone. Please remember to access homes south of Broadway from Summit and homes north of Broadway from Sherman.