Underground utility work continued this week on Wood Street with sanitary sewer installations from Hart to State Street. Additional road removal began on Dryden in preparation for sanitary sewer installation, which will take place the beginning of next week.
Work Completed last Week
- Water main tie-in completed at Woodlawn and Dryden.
- Sanitary sewer main installation on Wood from Hart Street to State Street.
- Sanitary lateral installation on Wood from Hart to State.
- Road removal continued on Dryden in anticipation of sanitary sewer installation
Anticipated Work Next Week
- Sanitary sewer main installation will continue on Dryden Street.
- Sanitary sewer lateral installations will begin on Dryden.
- Storm sewer installation will begin on Wood
Please Note: Undergrond utility work continues on Wood street. Dave’s party store is accessible on Hart Street from the north.