Progress Report

This week:

  • Schippers finished switching all the existing water service north of Brisam Street to the temporary water system.
  • Schippers started to install new 12-inch water main on Bonneville Drive north of Brisam Street.
  • Schippers subcontractor, Lees Trenching, finished installing new water services on Rockvalley Drive.
  • Schippers spread topsoil along Bonneville Drive and Bonanza Drive between 5 Mile Road and Brisam Street.

 

Next week:

  • Schippers will continue to install water main north of Brisam Street.
  • Schippers will start to reconstruct the road on Rockvalley Drive.

 

Schippers is working with their paving subcontractor, Black Gold, to get final paving on Rockhill Drive scheduled and schedule the base course paving on Rockvalley Drive as soon as possible. We are in the peak of the construction season which means contractors are very busy. Thank you for your patience as we work to get this completed.

 

What to Expect

July
  • Paving on Rockvalley Drive and Rockhill Drive.
  • Water main construction on Bonneville Drive, north of Brisam, and court streets.
 
August
  • Water service construction on Bonneville Drive, north of Brisam, and court streets.
 
Long Term
  • Schippers’ overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late summer. Schippers is currently on track to meet this schedule.

 

Important Information

There will be times that the area in front of your homes is torn up and you will have limited access to your home. Please let us know if you have any special access needs and we will do our best to make arrangements with you.

The contractor has set up a bank of temporary mailboxes on Brisam Street, west of Bonneville Drive. If you are within the construction area, your mail service has been temporarily relocated to here. The contractor is also coordinating with the trash haulers in the area to ensure that the trash is picked up during construction. Please bring your cans to the end of your driveway as you typically would, and the contractor will move them as necessary for pickup and return them at the end of the day.

 

Project Timeline

  • July 
    • Water main construction in Bonneville Dr. north of Brisma St.
    • Road reconstruction in Rockvalley Dr. and Rockhill Dr.
  • July – end of September
    • Water main and water service construction on Bonneville Dr. and court streets north of Brisam St.