Progress Report

Last week:
  • CL Trucking did not lay any water main beginning of last week as they were waiting for more pipe to arrive.
  • CL Trucking completed water main construction on Sprucewood Drive and Sprucewood Court.
  • CL Trucking completed water main construction through the easement between Sprucewood Drive and Frond Street.
This week:
  • CL Trucking will complete water main construction on Frond Street to Herrington Avenue.
  • CL Trucking will start water main construction on Pine Hill Drive.

 

Residents should have received a letter from Plainfield Charter Township explaining the process for installing the private portion of their new water service. You should get a contractor lined up as soon as possible to ensure that you meet the sixty (60) day connection requirement. If you have any questions about the process, please call Jeremy Kamp at (616) 432-6709.

 

What to Expect

July
  • Water main construction on Frond Street, and Pine Hill Drive
August
  • Water main construction on Belmont Avenue
  • Water main construction on Terrie Lynn Drive, Meek Drive, and Korben Woods Court
Long Term
  • Estimated project completion date: October 17, 2021

 

Project Timeline

  • Late-July – Early-September
    • Water Main Construction on Sprucewood Drive, Sprucewood Court, Frond Street, Pine Hill Drive and Belmont Avenue
  • Late-August
    • Water Main Construction on Terrie Lynn Drive, Meek Drive, and Korben Woods Court
  • September
    • Water Service Installation
  • October
    • Road Reconstruction, Driveway Reconstruction, and Lawn Restoration