This Week:

  • B&L Excavation has been waiting on Miss Dig to mark the existing utilities on Freska Pines which has delayed their start to water main construction on this private road.
  • Black Gold was on site at Squirewood to pave the road patches and replace asphalt driveways.
  • Concrete crews were on site Thursday to start forming sidewalk on Squirewood Drive.
  • The first section of concrete sidewalk is scheduled to be poured today (Friday).

 

Next Week:

  • B&L will begin water main construction on Freska Pines pending Miss Dig flagging is completed.
  • Concrete sidewalk and driveways on Squirewood Drive will continue to be replaced next week.

 

Please contact any project representative if you have questions or concerns.