This week, both projects are back in full swing. Al’s Excavating is out on Airway Street working on the preliminary grading and earth work. They started at Hunsburger and are working their way toward Plainfield Avenue. They are removing the topsoil and roughly grading the aggregate base as they move along.

Next week, they will move across Jupiter and continue the earth work. By the end of next week, the contractor plans to come back through and finish grading the pathway in preparation for asphalt.

On Jericho, subcontractor 28 Specialties has continued to construct the first of several large block retaining walls. They will continue the wall building process for the next few weeks. Once the earthwork crew wraps up on Airway Street, they will begin doing the grading work on Jericho.