Work Anticipated Week of July 24, 2023
- Contractor will set up road closure signs
- Manhole covers will be lowered in the roadway
- Roadway pavement will be removed on Tuesday, July 25, 2023
- Additional removals will take place
- Materials and equipment will be delivered to the site
- Underground pipe will begin to be installed
Work Anticipated Week of July 31, 2023
- Water Main Pipe will begin to be installed
- Storm Sewer pipe and drainage structures may be installed