Progress Report

This week:
  • Schippers completed water main installation north of Brisam Street.
  • Concrete driveway restoration was completed on Bonneville Drive and Bonanza Drive, south of Brisam Street.
  • Schippers began spreading road gravel north of Brisam Street.
  • Schippers worked on installing new sanitary and storm manhole covers and catch basin covers south of Brisam Street in preparation for final top course paving.
  • Schippers pressure tested and disinfected the new water main north of Brisam Street.
  • The Plainfield Water Department will obtain samples today and tomorrow for testing to ensure that the water main has been properly disinfected.
Next week:
  • Schippers will install the small piece of water main at the northeast corner of Plainfield Avenue and 5 Mile Road.
  • Pending passing samples this week, Schippers will start to install new water services next week north of Brisam Street.

 

What to Expect

July
  • Final top course paving on Rockvalley Drive.
  • Water main construction at the northeast corner of Plainfield Avenue and 5 Mile Road.
August
  • Water service construction on Bonneville Drive, north of Brisam Street, and court streets.
  • Road reconstruction north of Brisam Street.
Long Term
  • Schippers’ overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late summer. Schippers is currently on track to meet this schedule.

 

Important Information

There will be times that the area in front of your homes is torn up and you will have limited access to your home. Please let us know if you have any special access needs and we will do our best to make arrangements with you.

The contractor has set up a bank of temporary mailboxes on Brisam Street, west of Bonneville Drive. If you are within the construction area, your mail service has been temporarily relocated to here. The contractor is also coordinating with the trash haulers in the area to ensure that the trash is picked up during construction. Please bring your cans to the end of your driveway as you typically would, and the contractor will move them as necessary for pickup and return them at the end of the day.

 

Project Timeline

  • July
    • Water main construction at the northeast corner of Plainfield Ave. and 5 Mile Rd.
    • Final paving in Rockvalley Dr.
  • July — Late-September
    • Water service construction on Bonneville Dr. and court streets north of Brisam St.