Progress Report

This week:
  • Dykema completed sprinkler restoration. If you still have issues with your sprinklers, please contact a project representative.
  • Dykema hydroseeded Stoneridge Drive and the 43 North neighborhood.
  • Dykema prepped 11 Mile Road and Elstner Avenue for base course paving.
  • Base course paving is schedule for today (Friday), but is dependent on the rain forecast for the rest of the day.
  • Private water service contractors continue to install the private portion of the water service into residents homes.
Next week:
  • Dykema will work on lawn restoration along 11 Mile Road and Elstner Avenue.
  • Final top course paving on 11 Mile Road and Elstner Avenue is scheduled for Saturday, July 31st.

 

If you have not already contacted a private water service contractor to install your water service into your house, you should do that as soon as possible to ensure that you can meet the 60-day connection requirement.

 

What to Expect

July
  • Road reconstruction along 11 Mile Road and Elstner Avenue.
August
  • Final lawn restoration and project clean up.

 

Anticipated Project Timeline

  • July — August
    • 11 Mile Road and Elstner Avenue restoration