Progress Report

This week:
  • CL Trucking completed water main installation along Herrington Avenue.
  • CL Trucking started water main installation along Pine Hill Drive.
  • CL Trucking is not installing any water main today, they are going to focus on cleaning up the project site.
Next week:
  • CL Trucking will start to install water main along Belmont Avenue next week.

 

Residents should have received a letter from Plainfield Charter Township explaining the process for installing the private portion of their new water service. You should get a contractor lined up as soon as possible to ensure that you meet the sixty (60) day connection requirement. If you have any questions about the process, please call Jeremy Kamp at (616) 432-6709.

Please contact any project representative if you have questions or concerns.

 

What to Expect

July
  • Water main construction on Belmont Avenue
August
  • Water main construction Pine Hill Drive
  • Water main construction on Terrie Lynn Drive, Meek Drive, and Korben Woods Court
September
  • Water service construction
Long Term
  • Estimated project completion date: October 17, 2021

 

Project Timeline

  • Late July – Early August
    • Water Main Construction on Pine Hill Drive and Belmont Avenue
  • Late August
    • Water Main Construction on Terrie Lynn Drive, Meek Drive, and Korben Woods Court
  • September
    • Water Service installation
  • October
    • Road Reconstruction, Driveway Reconstruction, and Lawn Restoration