Progress Update

This past week was the first full week of watermain installation. Watermain installation started at Plaza Drive (the west end of the project). Watermain installation has progressed to just east of Berrien Avenue, in front of Care Dentistry. Approximately 500 feet of watermain has been installed to date, which is about 15% of the total 3,200 feet involved on the project.

 

Up Next

During the next week, watermain installation will continue to the east along the south side of Napier Avenue. Watermain installation will be continuing for several more weeks before reaching Pipestone Road (the east end of the project).