Dykema finished installing water services along Herrington Avenue this week. This marks the completion of all water main and water service stub installation for the project.

Dykema continues to work on restoration by fine grading ditch lines, spreading topsoil, and preparing to seed the lawns and roadside areas. Dykema also has started to complete concrete and gravel driveway restoration and is working on preparing the asphalt driveways for final paving.

A total of 6 houses have now connected to the municipal water system (see project map above). Water service quotation forms have been received for about 90% of the houses along Chandler and Herrington. If residents have not yet made arrangements with a contractor to complete the private water service work, they must do so as soon as possible. Some residents are already half-way through their 60-day time window.

 

What to Expect Next Week (July 27 – August 1)

 

Projected Timeline