Work completed this week:

  • Approximately 200 feet of 4-inch sanitary sewer installed and air tested.

 

Summary of activities expected for next week (July 27 – August 1):

  • Continue 48-inch sanitary sewer installation.
  • Temporarily restore Union Pier Road intersection east of Red Arrow Highway and
    **Re-open to traffic**.