Hallack Contracting spent this week installing sanitary sewer east of James Street. Utility work will continue for the next few weeks.
Work Completed This Week (July 20 – 24)
- Hallack Contracting completed the sanitary sewer from James Street to Harrison Street
- Hallack and City crews worked to verify sewer and water service locations.
Anticipated Work Next Week (July 27 – 31)
- Work will focus on installing sanitary sewer from Harrison Street to Delia Street.
- Signage from Rath Avenue to James Street may be completed.