This week, the contractor completed water main installation from Madison to Vulcan Street along with new hydrants (not yet in service) at Austin, Valley, and Madison.

Here is what to expect next week, the week of July 29, 2019

Remember that all work is weather dependent.

One paved lane remains for accessing homes and businesses on Broadway within the construction zone.  Please remember to access homes south of Broadway from Summit and homes north of Broadway from Sherman.