Progress Report:

This week Milblocker continued installing water main along Miramar between Eldon and Airway. The first section of new water main between Eldon and Daylor was filled with water and pressure tested on Friday. A second crew was on site this week to begin restoration work along Eldon. Portions of the concrete curb and gutter and sidewalk were installed along Eldon on Thursday. Milbocker plans to continue water main installation along Miramar on Saturday.

Upcoming Work:

Next week Milbocker will complete water main installation along Miramar up to Airway. After this is complete they will start installing water main along Miramar at Eldon and work south to Plainfield Avenue. The sections of new water main along Miramar north of Eldon will be pressure tested and disinfected in preparation for water service installation. Milbocker will continue with concrete and lawn restoration work along Eldon.