Work completed/in progress from the last update:

  • Transmission main between 152nd and western drill pit passed pressure test and is being connected to the drilled pipe.
  • Pigged pipe drilled beneath Pine Creek.
  • Transmission main installation in 144th Ave intersection complete and progressing to eastern drill pit.
  • Road paving and incidental concrete work between 152nd and western drill pit.
  • Road resurfacing project between Lakeshore and 144th started removals and concrete improvements.

Anticipated activities for the upcoming week include:

  • Continue transmission main between 144th and River to Holland Charter Township maintenance building.
  • Continue transmission main installation to eastern drill pit.
  • Mill transitions between existing and new paved surfaces between 152nd and 144th.
  • Chlorinate and test transmission main between 152nd and eastern drill pit.
  • Install restraint collar(s) on HDPE pipe.
  • Pave 144th Ave intersection and re-open to traffic.
  • Shoulder and topsoil restoration between 152nd and 144th.
  • Commence easement storm sewer construction between 144th and Aniline for road reconstruct project.
  • Dewatering setups, lateral replacement, and water service replacement, as necessary.