Progress Report

Belmont Avenue will be closed to thru traffic through next Friday, August 6. Please follow the posted detours around the construction areas.

Packer Drive will be closed to thru traffic through the end of October.

Due to the scare availability of 8-inch ductile iron water main pipe, CL Trucking has had to switch gears a couple of times over the last week between installing new water main and installing new water services. CL Trucking plans to continue installing water main when they have pipe available. Testing and disinfection of the new water main will be completed as they are installed. Water service installation will follow passing tests when time allows. You will be given an approximate time window of when your water service will be available for connection when you receive your approved Quotation Form. However, please be aware that the time frame is only approximate and may change based on water main pipe availability.

This week:
  • CL Trucking completed water service installation along Herrington Avenue.
  • CL Trucking started water service installation along Sprucewood Drive.
  • CL Trucking started water main installation along Belmont Avenue in order to coordinate this work with the Belmont Avenue closure.
Next week:
  • CL Trucking will complete water main installation along Belmont Avenue and Pine Hill Drive.

What to Expect

August
  • Water main construction on Pine Hill Drive and Belmont Avenue
  • Water main construction on Terrie Lynn Drive, Meek Drive, and Korben Woods Court
  • Water service construction
September
  • Water service construction
Long Term
  • Estimated project completion date: October 17, 2021

Project Timeline

  • Early August
    • Water Main Construction on Pine Hill Drive and Belmont Avenue
  • Late August
    • Water Main Construction on Terrie Lynn Drive, Meek Drive, and Korben Woods Court
  • September
    • Water service installation
  • October
    • Road reconstruction, driveway reconstruction, and lawn restoration