Work completed this week:

  • Approximately 250 feet of 48-inch sanitary sewer installed and air tested.
  • Manhole #5 installed.
  • Union Pier temporarily restored and opened to traffic.

 

Summary of activities expected for next week (August 3 – 8):

  • Continue 48-inch sanitary sewer installation.

 