Progress Report

Last week the crew finished up the retaining wall along Leonard Road. This week we had three crews in operation on the trail. The crew began building one of the remaining three retaining walls back in the woods. While the earth work crew worked on grading the pathway in preparation for gravel. The Boardwalk Crew began driving piles for the farthest boardwalk on Tuesday and expect to finish next week.

 

What to Expect Next Week

Next week crews will still be working in the wooded section of the path behind the golf course. They will begin again down Leonard Road if we get a lot of rain that slows the progress through the woods.