It has been a while since our last update. Since then, the focus has been on reconstructing West Street.
Work Completed on West
- The first course of pavement was installed.
- Concrete drives were installed.
Work Completed on Center
- Topsoil and cleanup was completed.
Anticipated Work on West
- Paving of the top course of asphalt.
- Spreading of topsoil.
- Following paving the aggregate shoulders will be placed.