This was a short week but some important items were completed. Next week will see less activity with the focus on water services. All of the water services on Wilcox need to be replaced before the sanitary sewer can be finished and the storm sewer can be replaced, which is the next major step.
Work Completed This Week
- Connection of the new Wilcox water main at Walnut and Edgewater was completed.
- Sanitary sewer installation continued east of Walnut.
- Water service installation continued on Cherry and started on Wilcox.
- Spreading of topsoil began on Thompson and Walnut.
Anticipated Work
- Water service installation will be the primary focus this coming week with services being installed on Wilcox and Cherry Streets.
- Manhole covers will be installed on Thompson and Walnut.