This Week:

  • Brenner Excavating worked on the water main crossing the Freska Lake Drain this week. Groundwater has been an issue at this location and has slowed progress. Brenner Excavating is going to continue to try to complete the crossing today (Friday) but may push it off until dewatering equipment can be set up next week.

 

Next Week:

  • Brenner Excavating will continue water service stub installation between Pine Island Drive and the Freska Lake Drain pending passing test results.
  • A dewatering contractor will be on site middle of next week to install dewatering equipment at the drain crossing.
  • The last of the 16-inch water main will be installed across the Freska Lake Drain the following week.

 

Please contact any project representative if you have questions or concerns.