This Week:
- B&L Excavation completed the water main tie-in to the existing stub at 10 Mile Road which was installed by Brenner Excavating earlier this spring.
- B&L Excavation began installing water service stubs towards houses on Squirewood Drive.
Next Week:
- B&L Excavation will complete water service stub installation on Squirewood Drive and Squirewood Court early next week.
- Concrete sidewalk on Squirewood Drive will be replaced.
- Concrete driveways on Squirewood Drive and Squirewood Court will begin to be replaced.
Please contact any project representative if you have questions or concerns.