This Week:
- The remaining driveway and shoulder work along Pine Island Drive was rescheduled to this Saturday (7/8).
- A portion of the southbound lane in Pine Island Drive will also be repaved to fix damage from construction on Saturday. Pine Island Drive will be flagged during the paving as only one lane of traffic will be maintained – delays can be expected.
- Montgomery continued restoration work throughout the project.
- Pine Island Court gravel is being graded today (Friday) in preparation for paving next week.
Next Week:
- Black Gold will be on site Monday morning to pave the base course of Pine Island Court.
- The top course (final) paving of Pine Island Court will be completed middle of next week.
- Montgomery will complete final restoration and final project cleanup.
Please contact any project representative if you have questions or concerns.