Here is a quick update on the progress of construction on Leahy Street between Sherman and Barney in Muskegon Heights.

 

Work Completed This Past Week

  • The final water main connections were completed at Barney and Leahy
  • All underground utility work is complete

 

Work Anticipated Week of July 10, 2023

  • Surveying and staking for the new roadway will begin
  • Crews will begin cutting the road down to the appropriate depth of road base gravel and begin placing gravel on the roadway
  • Additional removals of any loose sidewalk or driveway pieces will be completed
  • The edge of the road will be located for the new concrete curb and gutter

 

Work Anticipated Week of July 17, 2023

  • Continued work on cutting the road, adding road gravel, grading and compacting and preparing for new concrete curb and gutter