This past week, crews began delivering equipment and materials to the job site and are preparing to begin construction next week.
Work Anticipated Week of July 10, 2023:
- Detour signs will be installed and the road will begin to be closed
- Removals of items outside the roadway will begin
Work Anticipated Week of July 17, 2023:
- Removals of pavement, curb and gutter and preparation for the storm sewer installation will begin