Progress Report:

  • Maple St. Storm Sewer: Storm sewer installation on Maple Street between Fremont and Lincoln Street was completed this week. Storm laterals on Maple Street are planned to begin this week with additional work to be performed on Saturday. Storm lateral installation is planned to continue the following week.
  • Lincoln Street: Water service and sanitary lateral installation along Lincoln Street is in process and is planned to continue next week.

 

Overall Progress:

The project remains on track with the original project schedule. The northern part of Lincoln Street from Courtland Street to the Middle School driveway is expected to be completed before school is in session. Completion of the entire project is expected in early October.