This Week:

  • Montgomery installed 8-inch water main across Jewell Avenue at Green Timbers Drive.
  • Montgomery began filling the water main in Jewell Avenue and Green Timbers with water in preparation for pressure testing.
  • Montgomery continued installing 12-inch water main along Jewell Avenue.
  • Jewell Avenue was closed to thru traffic.

 

Next Week:

  • Montgomery will continue installing 12-inch water main along Jewell Avenue.
  • Montgomery will begin to pressure test and disinfect the first section of water main between 10 Mile Road and Offroad Drive.
  • Jewell Avenue will be closed to thru traffic.

 

Week of July 18:

  • Montgomery will have a second crew on site to begin installing water main in the Cottages on the Rogue neighborhood.
  • Montgomery’s first crew will continue to install water main along Jewell Avenue.

 

Please contact any project representative if you have questions or concerns.