Progress Update

Water main installation for the remainder of the project is complete. The new water main is now in process with disinfection, flushing, and bacteriological testing. These are standard public health procedures for new water main construction. The site grading needed to prepare for road restoration has begun.

 

Up Next

During the next week the disinfection, flushing, and bacteriological testing procedures should be complete and water service lines will be installed.  Road restoration work is also upcoming, with concrete pouring anticipated by mid-week.