This past week, the Contractor worked on:

  • Continued with the installation of bricks in the decorative crosswalks at Sanford

 

We are nearing the end, but please remember that left hand turns are not allowed at most intersections and signs are in place.  Please keep our workers safe and follow all traffic control rules within the construction zone.

 

Work Anticipated for the Week of July 12, 2021:

Although most of the bricks appear to be done, there is some correction work that needs to take place at the Peck and Baker intersections with the bricks.  This will require a traffic shift back to the south side of Sherman Boulevard for about two weeks.  Once the bricks are re-set, the project will be completed.  The traffic shift is tentatively scheduled for around Noon on Monday, July 12, 2021.

  • Bricks will be re-set on the north side of Sherman at Peck and Baker
  • Bricks will be re-set across Baker at Sherman

 

Baker will be closed again at Sherman with a detour to Sanford which will be re-opened.