Progress Report

This week:

  • Schippers completed the water main installation in Rockvalley Drive and through the private easements between Rockvalley Drive and Bonneville Drive.
  • Schippers continued to rebuild the road on Bonanza Drive and the south half of Bonneville Drive.
  • Schippers subcontractor, Martin J Construction, poured concrete curbs on Bonneville Drive and Bonanza Drive.

Next week:

  • Due to weather delays, base course paving in Rockhill Drive is rescheduled for next week.
  • Schippers will continue to reconstruct the road on Bonneville Drive and Bonanza Drive in preparation for paving later this month.
  • Schippers will work on setting up the temporary water main on the north half of Bonneville Drive and the court streets.
  • Schippers will pressure test and disinfect the newly installed water main in Rockhill Drive in preparation for water service construction the following week.

 

What to Expect

June
  • Road reconstruction on Bonneville Drive and Bonanza Drive south of Brisam Street
  • Temporary water main set up north of Brisam Street.
  • Water service construction on Rockvalley Drive.
July
  • Base course paving on Bonanza Drive and the south half of Bonneville Drive is scheduled to be completed prior to the Fourth of July.
  • Water main construction on Bonneville Drive, north of Brisam, and court streets.
August
  • Water service construction on Bonneville Drive, north of Brisam, and court streets.
Long Term

Schippers’ overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late summer. Schippers is currently on track to meet this schedule.

 

Important Information

There will be times that the area in front of your homes is torn up and you will have limited access to your home. Please let us know if you have any special access needs and we will do our best to make arrangements with you.

The contractor has set up a bank of temporary mailboxes on Brisam Street, west of Bonneville Drive. If you are within the construction area, your mail service has been temporarily relocated to here. The contractor is also coordinating with the trash haulers in the area to ensure that the trash is picked up during construction. Please bring your cans to the end of your driveway as you typically would, and the contractor will move them as necessary for pickup and return them at the end of the day.

 

Anticipated Project Timeline

  • June
    • Water main and water service construction in Rockvalley Dr.
    • Water service construction along Plainfield Ave.
    • Road reconstruction in Rockhill Dr, Bonneville Dr, and Bonanza Dr.
  • End of June – end of September
    • Water main and water service construction on Bonneville Dr. and court streets north of Brisam St.