Please see below for a construction update.  There has been significant work completed since the last update.

 

Work Completed (May 22 – June 11)

  • The fireplace has been set in place and looks fabulous.
  • Lighting is installed.
  • Colored concrete under and around the shelter is complete.
  • The shelter tongue and groove roof decking has arrived, and the roof is 75% complete.
  • Some of the decorative concrete in front of Spin Drift is being replaced due to surface discoloration.
  • The clock is back up at the north end of the site.
  • Restroom Building is nearing completion.

 

Work Anticipated Next Week (weather dependent)

  • Contractor anticipates getting plumbing, HVAC, and electrical inspection done next week.
  • The shelter will be completed by Wednesday.
  • A final review of the decorative concrete is planned for early next week.
  • A week from Monday the landscaper will be ready to install landscaping.