Work completed this past week:

  • Water main at Townline and Greenwood was temporarily relocated to allow installation of a deep sanitary structure. Water service for much of the area was suspended twice while temporary connections were made.
  • The deep sanitary structure at Townline and Greenwood was set and connections to the existing sanitary sewers made.
 
 

Potential activities expected next week (June 15 – 19):

  • Complete sanitary sewer installation in Union Pier intersection.
  • Transfer flow to new meter piping.
  • Complete sanitary sewer installation beneath Red Arrow Highway at Berrien Street.
  • Begin temporary restoration of Union Pier intersection.
  • Temporary suspension of water service for additional water main work. Advance notice will be provided.