All the water services stubs have been installed to the right-of-way line, which means water service is available for all residents.
Five houses in the neighborhood already are connected to the Township water system. You may schedule the work to hook up to your water service as soon as you have received an approved Quotation Form. As of June 10, about 80% of residents have approved to proceed. For tracking purposes, the construction status map has been modified to show a property as “Connected” as soon as the water meter is set and the plumbing is connected to the water system.

Concrete driveway replacement continues, and Bultsma hopes to have all concrete driveway and sidewalk replacement completed this week. Lawn restoration is underway.

The base course of asphalt at the water main road crossings was scheduled to be paved yesterday, June 11.

 

What to Expect Next Week (June 15 – 20)

 

Projected Timeline