  • Watermain has been placed along Burger between Goodwood and Tanglewood.
    • The main has passed all testing and has been tied into the existing system.
    • Crews have completed stubbing water services out to the right-of-way line.
  • Watermain has been placed along Tripoli between Burger and Tuscany and on Tripoli Court.
    • The main has passed all testing and has been tied into the existing system.
    • Crews have completed stubbing water services out to the right of way line.
  • Watermain has been placed along Cimarron between Goodwood and Tuscany.
    • The main has passed all testing and has been tied into the existing system.
    • Crews have completed stubbing water services out to the right of way line.
  • Watermain has been placed along Burger between Tanglewood and the west end of the job limits (6950 Burger).
    • The main has passed all testing and has been tied into the existing system.
    • Crews have completed stubbing water services out to the right of way line.
  • Watermain has been placed along Tuscany between Burger and the west end of the job limits.
    • The main has passed all testing and has been tied into the existing system.
    • Taps are being completed this week.
  • Contractor has completed the installation of the new storm sewer on Burger between Tanglewood and the bayou and between Tuscany and 6920 Burger.
  • Restorative efforts are continuing, and damaged irrigation systems are being repaired.

 

Work Upcoming

  • The contractor will complete stubbing water services along Tuscany between Burger and the cul-de-sac.
  • Watermain installation on Tanglewood is also slated to begin the week of June 19, starting at the Burger Dr intersection moving south/west
  • Crews will continue restorative efforts in completed areas.

 

General Notes

  • Residents should be aware that after your yard has been dug it may be up to a month before we are able to complete the work and repair irrigation systems.
  • The contractor will be responsible for establishing grass growth.  For best results residents are encouraged to regularly water the hydroseed and mow down any weeds that do come in.