Work Completed This Week

  • Finished all concrete improvements on Phase 1 (Southern Ave to Merrill Ave).
  • Continued replacing sanitary sewer laterals on Phase 2 (Laketon Ave to Southern Ave).
  • Fine graded the aggregate base and paved the base course and leveling course of asphalt on Phase 1.
  • Began raising manhole castings in the roadway up to final grade.
  • Installed all 8-inch mainline water main on Phase 2 and began chlorinating the water main after passing pressure testing.

 

Anticipated Work Next Week

  • Pulverize the asphalt on the south half of Dale Avenue on Monday and install the 36-inch storm sewer on Dale Avenue to Clinton Street.
  • Tie-in the new water main on Phase 2 after bacteria testing is completed.  Water service replacements may begin before the end of the week.
  • Finish replacing the sanitary laterals on Phase 2.
  • Raise all manhole castings on Phase 1 before possibly paving the top course of asphalt near the end of the week.
  • Place top soil over disturbed areas in Phase 1.