DeSal Excavating has installed water main to approximately 1850 House Street. At this time, they have installed a total of about 6,300 feet of 16-inch water main (about 70% of the contract) from Pine Island Drive to the east. They have completed this footage in about 5 weeks, averaging just over 300 feet of pipe installed per day.

DeSal has installed water service stubs along Pine Island and at the west end of House Street for the first couple dozen properties. These homes will be notified next week that their water service is available for connection.

DeSal had a street sweeper on site yesterday to clean the road, which will help minimize the dust. Due to the hot and dry weather, the sweeper will come out as needed to keep the road as clean as possible.

 

What to Expect Next Week (June 22 – 27)

 

Projected Timeline