K&R and Black Gold have been working this week with the Kent County Road Commission and Prein&Newhof to develop a plan for the road repairs. You will have noticed the spray paint on the road which is a result of this planning work.
Road repairs are set to take place and be completed next week. Manhole covers will be lowered on Monday, milling will take place Tuesday, manholes will be adjusted Wednesday, and paving will take place Thursday. Select driveways which need to be replaced will not be completed until after June 12 to allow time for the new road surface to cool off.