This Week:
- Montgomery began water main construction at Childsdale Avenue and is working towards the cul-de-sac.
- A gas service and electrical line were hit this week during construction and repaired by DTE and Consumers Energy.
Next Week:
- Water main construction will continue next week, and it is anticipated that all of the water main will be installed by the end of the week.
- Montgomery will fill the new water main with water in preparation for testing to be completed the following week.
Please contact any project representative if you have questions or concerns.