This week, the focus was on concrete, and approximately 80% of the concrete for the first phase has been placed. Final grading of aggregate has begun with paving of the roadway just around the corner. NOTE: Phase II will begin starting June 9. At that time, the detour will be extended and Sanford will be closed from Apple to Southern.

 

Work Completed This Week

  • Contractor placed curb & gutter radius’ at intersections.
  • Contractor placed sidewalk and drive approaches.
  • Contractor began grading aggregate in preparation of paving.

 

Anticipated Work Next Week

  • Continue placing sidewalk and drive approaches – should be complete by mid-week.
  • Continue fine grading of aggregate grade in preparation of placing asphalt pavement.
  • Placing first course of asphalt pavement on Wednesday.
  • Placing manhole castings and watermain valve boxes to finish grade, in preparation of placing top course of asphalt.
  • Begin performing turf restoration for Phase I.