Milbocker has completed:
- Driveway and sidewalk removals along Eldon.
- Removed the topsoil along Eldon in preparation for water main construction.
- Water main construction along Eldon between Hunsberger and Northgate.
- Curb replacement at the Eldon/Hunsberger intersection in coordination with the KCRC project to repave Hunsberger.
Chop has removed all of the trees for water main construction along Eldon and Miramar.
Upcoming Work:
Milbocker will continue to install water main along Eldon next week. There will be times when Northgate and Miramar are closed next week to allow for the new water main to be installed across the road. Please drive around the work area while these closures are in place.