Remaining Work:
- Black Gold is scheduled to be on site MONDAY, JUNE 26, to complete the milling and repaving of the asphalt driveways.
- K&R will be on site end of next week and will touch up lawn restoration along the road and driveway edges prior to the July 4th
Please contact any project representative if you have questions or concerns.